Configure your lobby
Train Puling Locations | Configure Rest | Configure yards | Configure Routes | Training Locations | Holidays | L.R due period |

 

The Level 2 user, the lobby super user or the configuration manager can configure the lobby under his control to suit his requirement. The various parameters that can be configured are as below

Train Pulling Locations

Train pulling times are different for different lobbies. CMS allows the train pulling time to suite a Lobby requirement. A typical example of the data entry screen for Train pulling is shall be

Location Name
Pulling time for Guards
Pulling time for Loco Staff
RTM main line
30 min
15 min
RTM UP Yard
45 min
30 min
RTM DN Yard
35 min
25 min

A station code has been added before the Train pulling location essentially from CMS 1.6.0 onwards. This shall facilitate the crew to sign on at the station code appearing prior to the train pulling location. For example A lobby like Ghorpuri GPR can make a Train pulling location GPR – Mainline or PUNE – Mainline. When a TA is made for GPR-Mainine the crew can sign on at GPR with a call server from GPR while if the train pulling location is PUNE-Mainline then the crew can sign ON at PUNE for a call server from GPR lobby.

All such lobbies like GPR-PUNE, BSLX-BSL, BRCY-BRC are termed as sister lobbies by the CMS software.

The minimum pulling time is 15 min and the max pulling time is upto 1 Hr is the limit provided.


Configure Rest

The rest types can be configured from the configuration manager. The user has to select the rest type from one of the below mentioned rest options.

Type – I sections (Like RTM divn)

Duty Hrs - Rest at HQ - Rest at outstation
< 8 Hrs - 12 Hrs Rest-2/3 rd of the duty performed.
>= 8 Hrs duty-16 Hrs Rest-8 Hrs Rest (Staff may opt for 6 Hrs rest).

Type – II sections (Like Hajipur divn)

Duty Hrs - Rest at HQ - Rest at outstation
< 5 Hrs-12 Hrs Rest- Actual duty Hrs + 1 Hr
>=5 to < 8 Hrs - 12 Hrs Rest- 6 Hrs
>= 8 Hrs duty -16 Hrs Rest- 8 Hrs Rest (Staff may opt for 6 Hrs rest).

Type – III sections (Like Bombay divn)

Duty Hrs - Rest at HQ -Rest at outstation
< 8 Hrs -12 Hrs Rest- ½ of the duty performed.
>= 8 Hrs duty- 16 Hrs Rest -8 Hrs Rest (Staff may opt for 6 Hrs rest).

Type – IV sections (Like SWR)

Duty Hrs - Rest at HQ- Rest at outstation
< 8 Hrs - 12 Hrs Rest- 1 + duty Hrs performed.
>= 8 Hrs duty- 16 Hrs Rest- 8 Hrs Rest (Staff may opt for 6 Hrs rest).

Type – V sections (Like NFR)

Duty Hrs - Rest at HQ- Rest at outstation
< 8 Hrs - 12 Hrs Rest- 4 Hrs.
= 8 Hrs duty- 16 Hrs Rest- 4 Hrs.
> 8 Hrs duty < 10 Hrs - 16 Hrs Rest- 6 Hrs.
>= 10 Hrs duty- 16 Hrs Rest- 8 Hrs.

  1. These rests shall be given by the system itself from the information as available in the database.
  2. In case of outstation rest, the crew can opt for 6 Hrs rest by selecting appropriate option available on the KIOSK
  3. The staff can, however, be called in breach of this limit (according to his rest) in cases of accidents or breakdowns. The supervisor has full power to call them. In such case the book crew all option is selected to display the under rest crew also getting highlighted in light gray.
  4. All rests shall be in Hrs only.

Configure Yards

The yards where the shunting operation takes place can be configured as per the user requirement. The yards can have sub yards. Each yard is a subset of itself. This activity is mainly required for Shunting operations where a Shunter has to go to a yard for carrying out shunting duties in specific yard, which may be subset of that another yard. It is recommended that this activity is carried out in consultation with CRIS C3 support or by coming to CRIS for making the respective Yards and Routes.

Top Λ

Configure Routes

CMS super users can configure the Routes to suite his local requirements from the configuration manager link. The user can control the display of routes or the stations in his routes to suite his local requirement for

  1. Traffic advise.
  2. Manual crew booking
  3. Bio data
  4. Caution order

In case the route is ticked it shall be displayed in case it is unchecked the display shall stop. However it is essential that all the routes are available in the CMS system that were created by the user by coming to CRIS. If the route does not exist in CMS database it can not be configured.

Training Locations

The training Locations (Outstation Location) are the locations where the running staff go for purpose of duty, training, enquiry etc. Apart from the stay at these location the to and from allowance is also admissible to the running staff in terms of to an from km's. All the possible locations where the running staff can go are configured as follows

Training Location Admissible to and fro km's
ABR
92
BRC
130
KOTA
160

Holidays

For the complete calendar year the Holidays are configured into the system. If the running staff works on the holiday he shall be admirable for km's as per standard rules. List of all the Holiday for the current year must be configured into the system for the entire year to take the benefit of this rules.

L.R. Due periods

Some of the railways is 3 month LR updating while others use 6 months for LR updating. 3 or 6 Months must be configured into the system to take effect.